Page review information
Edition covered
General controls project practice — no single governing document — n/a — practice-level stage guidance; editions are recorded on the standards pages
Content status
Reviewed
Coverage
General project lifecycle (requirements through handover) and how the functional-safety lifecycle overlays it; practice-level only.
Last reviewed
August 2026
Primary reference
The official published standard — required for final decisions

Confirm the governing edition, jurisdiction, and project-specific requirements before applying anything on this page.

The General Flow

Every control-system project — a conveyor upgrade, a new machine, a process skid — moves through the same broad sequence, whether or not it contains safety functions:

flowchart LR
    A[Requirements] --> B[Architecture]
    B --> C[I/O & Instrumentation Design]
    C --> D[Electrical Design]
    D --> E[Software Design]
    E --> F[Panel Build]
    F --> G[Integration & FAT]
    G --> H[Installation]
    H --> I[SAT / Commissioning]
    I --> J[Handover]
    J --> K[Operation & Maintenance]
    K --> L[Management of Change]
    L -.-> A
Phase Typical activity Typical deliverables
Requirements Scope, process description, performance targets, constraints Design basis, URS
Architecture Control platform, network, panel count, I/O philosophy Architecture drawing, tag philosophy
I/O & instrumentation Instrument selection, I/O list, ranges, alarm strategy I/O list, instrument index
Electrical design Power distribution, protection, panel layout, wire sizing Schematics, panel layout, BOM
Software design Control narrative, sequence logic, HMI design Control narrative, cause & effect, code
Panel build Fabrication, wiring, point-to-point checkout Build records, checkout sheets
Integration & FAT Software-with-hardware testing at the factory FAT protocol and report
Installation Site installation, field wiring, terminations Installation records, loop-check prep
SAT / commissioning Loop checks, functional tests, performance runs Loop sheets, SAT report, punch list
Handover Documentation package, training, as-builts O&M package, as-built drawings
Operation & maintenance Preventive maintenance, spares, periodic tests Maintenance records
Management of change Controlled modification of anything above MOC records

Where the Safety Lifecycle Overlays It

When the project includes safety-related control functions — safety-rated devices, a PL or SIL target, a SIF, a CE-marked machine — the functional-safety lifecycle runs alongside and inside the general flow, adding analysis stages up front and verification gates throughout:

General phase Safety-lifecycle overlay
Requirements 1. Concept — machine limits and use cases
Requirements → Architecture 2. Standards Selection · 3. Risk Assessment · 4. Safety Requirements Spec
Architecture 5. Safety Architecture — PL/SIL verification of the proposed design
Electrical / software design 6. Detailed Design · 6b. Safety Wiring
Panel build → commissioning 7. Build through 10. Commissioning — with safety validation added to FAT/SAT
Operation & MOC 11. Maintenance (proof testing) · Management of Change

Two practical differences to keep straight:

  1. The safety lifecycle front-loads analysis. Risk assessment and the SRS exist before detailed design in a way general projects often skip — that is the point of it.
  2. The safety lifecycle adds independence. Verification gates are reviewed by someone other than the designer, to a degree that depends on the applicable standard and integrity level.

A project with no safety functions still benefits from the general flow’s discipline — it just doesn’t carry the safety gates.

Trust Boundary — Engineering Judgment Required

This site is an independent educational reference for industrial automation standards. It paraphrases and organizes guidance in original language; it is not a substitute for the official published standards, professional engineering judgment, or legal review, and content has not been independently verified against current published editions.

Items marked Review pending await technical review against the identified edition. Items marked Planned have no reviewed source material behind them. Do not rely on this site for compliance determinations, safety-critical design decisions, or legal interpretation.