Drive Commissioning
Pre-power
- Confirm the drive model matches the intended supply and motor application
- Confirm protective earth and bonding connections are complete
- Confirm line, load, braking, and control terminals are landed intentionally
- Confirm motor cable routing and shielding approach match the design basis
- Confirm the driven machine is safe for initial motion checks
Setup
- Record the motor nameplate data before parameter entry
- Enter or verify the required motor and control parameters
- Confirm the command source and stop behavior are understood
First power-up
- Power the drive in a controlled state
- Confirm no immediate faults or abnormal indications appear
- Confirm the drive can be safely inhibited or disabled if behavior is unexpected
First run
- Verify rotation direction using an approved low-risk test method
- Observe current, sound, vibration, and temperature trend during the initial run
- Stop and investigate immediately if abnormal behavior appears
Handover basis
- Save or record key commissioning parameters
- Record any tuning changes or restrictions for future maintenance
Follow site safety procedures and OEM instructions for stored energy, isolation, and enabled motion throughout.
Related Training
Related Workflows
Related Lifecycle Stages
This site is an independent educational reference for industrial automation standards. It paraphrases and organizes guidance in original language; it is not a substitute for the official published standards, professional engineering judgment, or legal review, and content has not been independently verified against current published editions.
Items marked Review pending await technical review against the identified edition. Items marked Planned have no reviewed source material behind them. Do not rely on this site for compliance determinations, safety-critical design decisions, or legal interpretation.