Page review information
Edition covered
Field verification practice — OEM instructions and the site electrical safety program govern — n/a — procedure-agnostic checklist
Content status
Reviewed
Coverage
Reminder-layer checklist for first powered motor check or reconnection; site procedures and LOTO govern.
Last reviewed
August 2026
Primary reference
The official published standard — required for final decisions

Confirm the governing edition, jurisdiction, and project-specific requirements before applying anything on this page.

Project
Date
Equipment
Technician
Location
Reviewed by
  • Confirm safe conditions for jog or brief start
  • Verify the driven equipment can tolerate rotation check
  • Jog the motor and confirm actual rotation direction
  • If rotation is wrong, correct the phase arrangement using the approved method
  • Observe current and overload behavior during initial run
  • Confirm overload does not nuisance-trip under expected no-load or light-load startup
  • Stop and investigate immediately if current, sound, vibration, or heating is abnormal

Do not convert a wrong-rotation discovery into repeated trial-and-error energization. Correct intentionally, then re-test.

Trust Boundary — Engineering Judgment Required

This site is an independent educational reference for industrial automation standards. It paraphrases and organizes guidance in original language; it is not a substitute for the official published standards, professional engineering judgment, or legal review, and content has not been independently verified against current published editions.

Items marked Review pending await technical review against the identified edition. Items marked Planned have no reviewed source material behind them. Do not rely on this site for compliance determinations, safety-critical design decisions, or legal interpretation.